A padel club business plan needs a timetable before it needs a turnover target. This worked example sells 4,580 court-hours a year across two outdoor courts, producing £120,300 of revenue excluding VAT. After running costs and the illustrated loan payments, it leaves £7,618 before tax and other cash movements. Closing one hour earlier on weekdays, without moving the affected bookings, turns that into a £1,937 annual cash shortfall. The permitted playing hours can decide whether the project works.

This is a hypothetical planning example, not an operating club or a forecast of UK market returns. The operator is a commercial limited company leasing a leisure site in England. It installs two uncovered, floodlit padel courts and a modest reception facility. It earns only pay-and-play court-hire income: no membership fees, café, shop, coaching sales or sponsorship are assumed. All prices, costs, occupancy and funding terms below are modelling inputs to replace with evidence.

The company is assumed to be VAT-registered throughout. Customer prices include the standard 20% VAT rate; revenue and costs are net of recoverable VAT. HMRC’s sports-facilities guidance includes exceptions for certain long lets and series of sessions, and separate rules for eligible sports bodies. This example assumes ordinary individual commercial court bookings, not an exempt members’ club.

Write the playing week into the plan

The proposed offer is simple: book a court online, see a clear total price and gain reliable access to a maintained playing surface. The operating assumption is 8am–10pm, seven days a week, for 50 trading weeks. Two weeks are held back for planned closures and major maintenance. These are proposed hours to verify against planning conditions, the lease and local demand; they are not permission to trade.

Peak time is defined as 5pm–10pm Monday to Friday and 10am–6pm at weekends. That gives 41 peak and 57 off-peak hours per court each week. Two courts therefore offer 4,100 peak and 5,700 off-peak court-hours over the modelled year.

Simulated annual court-hire plan — two courts, 50 weeks
BandAvailable court-hoursCompleted utilisationHours soldPrice per court-hour incl. VATNet revenue
Peak4,10070%2,870£36£86,100
Off-peak5,70030%1,710£24£34,200
Total9,80046.7% weighted overall4,580Two separate tariffs£120,300

A court-hour is one court occupied for an hour. Four people sharing that court do not create four separate court-hire sales. A 90-minute booking uses 1.5 court-hours; any turnaround allowance must also fit the schedule. The target averages 91.6 completed court-hours a week across both courts. Fractional annual averages are planning measures, not a claim about individual booking lengths.

Simulated completed utilisation: peak 70% of 4,100 available court-hours; off-peak 30% of 5,700 available court-hours.
Peak and off-peak percentages have different denominators. Together they sell 4,580 of 9,800 annual court-hours: 46.7% overall, not the simple average of 70% and 30%.

Completed utilisation must reflect weather-related cancellations, refunds and downtime as well as demand. Uncovered courts cannot be assumed to perform like indoor courts in winter. Before using the annual target, build a monthly schedule showing daylight, permitted lighting hours, closures and the sessions that can actually be delivered. A reserved slot that is later refunded is not a completed sale.

Prove the demand for the hours that remain empty

The commercial challenge is filling specific gaps, especially weekday daytime hours. A busy Friday evening does not prove demand at 11am on Tuesday. The plan should identify who can attend each band, how they will discover the club and what makes them book again. Beginner introductions, social play and local workplace groups are options to test; none is treated as a signed partnership here.

Map existing courts and approved or pending competing developments within the actual catchment. Compare dated tariffs, booking lengths, access arrangements, court cover and cancellation terms. An unavailable slot on a booking calendar might be blocked for maintenance or coaching: it is not proof of paid demand. Record enquiries and paid trial attendance, then follow repeat bookings by time band.

The £5,000 annual marketing budget below needs a costed programme with a review date. Measure completed court-hours acquired, their contribution and subsequent repeat play. If a promotion fills off-peak courts at a lower achieved price, rerun the revenue calculation using that price. Do not add a membership income line while leaving the same discounted or included court hours counted again at full pay-and-play rates.

Give every pound of court hire a job

The £36 peak price becomes £30 net revenue; the £24 off-peak price becomes £20. The timetable produces £144,360 of customer receipts, including £24,060 of output VAT before eligible input recovery. Output VAT is not revenue available to pay the owner.

The model allows 4% of net revenue for variable booking and payment costs (£4,812), plus £1.50 per completed court-hour for incremental lighting, wear-related supplies and other usage costs (£6,870). These are effective planning allowances, not a payment provider’s tariff or an electricity quote. Actual charges may depend on gross receipts, customer acquisition or lights running during unsold hours. Fixed site consumption is included in the site allowance below.

That leaves £108,618 of annual contribution: £120,300 less £11,682 of variable costs. Each additional peak hour contributes £27.30 and each off-peak hour £17.70 at the assumed prices and costs, provided no extra staffing or other fixed cost is triggered.

Illustrative annual cash operating costs — GBP
CostAllowanceEvidence needed
Owner-director remuneration and employer costs£30,000Paid management work included; confirm payroll treatment
Part-time operational cover and employer costs£20,000Cost the rota, leave, training and cover
Site rent, service charges and fixed utilities£18,000Lease, meter arrangements and landlord charges
Business rates£3,000Actual assessment and relief eligibility
Insurance£2,000Cover for activities, staff, site and equipment
Marketing£5,000Costed tests and repeat-booking evidence
Routine maintenance and cleaning£4,000Maintenance manual, contractor quotes and inspections
Booking/access subscriptions and administration£3,000Fixed subscriptions, connectivity and professional support
Total£85,000Inputs, not UK market averages

The staff budget does not mean a receptionist is on site for all 98 weekly opening hours. It assumes a management rota, part-time cover and remote access support. Specify supervised sessions, daily safety inspections, emergency response, first-aid arrangements and who attends a failed gate or lighting system. If the site or insurer requires more staffed hours, increase the payroll budget before accepting the forecast.

Profit and cash at the target annual timetable — simulated
MeasureGBPMeaning
Revenue excluding VAT£120,300Court hire only
Contribution£108,618After variable costs
EBITDA£23,618After £85,000 cash operating costs
Depreciation£21,000Illustrative asset allocation described below
Operating profit£2,618Before finance and tax
Interest£6,000Illustrative annual finance allowance
Loss before tax−£3,382Positive EBITDA does not make this a profitable plan
Loan principal repaid£10,000Cash movement, not a P&L expense
Cash after interest and principal£7,618Before tax, VAT timing, working capital and further capital spending
Amount left after earmarking £3,000 for replacement£4,618Earmarking retains money in the business; it is not another expense or external payment

This base case needs improvement before it supports a convincing investment decision. It produces a small cash surplus after the illustrated debt payments while showing a loss after depreciation and interest. The owner’s working remuneration is already included; the remaining cash is not an additional salary or a guaranteed distribution.

Test the last weekday hour before relying on it

Suppose the permitted weekday closing time is 9pm rather than 10pm, while weekend hours stay unchanged. The plan loses 2 courts × 5 hours × 50 weeks = 500 available peak court-hours. At the same assumed 70% utilisation for those withdrawn slots, 350 completed hours disappear. This scenario assumes the bookings are not moved elsewhere and no cancellation income is retained.

The contribution lost is 350 × £27.30 = £9,555. Fixed costs, depreciation and the illustrative debt payments remain unchanged.

Simulated effect of an earlier weekday closing time
Annual measure10pm weekday close9pm weekday close
Completed court-hours4,5804,230
Revenue excluding VAT£120,300£109,800
Contribution£108,618£99,063
EBITDA£23,618£14,063
Loss before tax−£3,382−£12,937
Cash after interest and principal£7,618−£1,937
Cash after also earmarking the £3,000 replacement allowance£4,618−£4,937
Simulated annual cash after debt: 10pm weekday closing £7,618; 9pm weekday closing minus £1,937, assuming no displaced bookings are recovered.
Removing the final weekday hour costs £9,555 of contribution at the assumed occupancy. Values exclude tax, VAT payment timing, additional capital spending and changes in working capital; the £3,000 replacement earmarking is shown separately in the table.

Recovering that contribution through off-peak sales alone would require about 540 additional completed court-hours a year at £17.70 contribution each. Off-peak utilisation would need to rise from 30% to about 39.5%, without another cost increase. That is a new demand target to prove, not an automatic transfer of evening players. Check the actual demand for the last hour separately: average peak occupancy may hide a different pattern late at night.

Fund the build and the period before the timetable fills

The illustrative funding pot is £260,000: £160,000 equity and a £100,000 commercial loan. Uses are £150,000 for installed courts, base and lighting; £30,000 for reception, access systems and equipment; £10,000 for deposit and other recoverable opening balances; £10,000 of pre-opening professional and launch costs; £40,000 operating cash; and £20,000 held as construction contingency. The two cash allocations remain separate. No grant is assumed.

These are budgets to replace with a site survey and itemised quotations. They do not buy land or an indoor building. Recoverable input VAT may still have to be paid before it is recovered: obtain a gross-payment and VAT-recovery schedule and fund that timing gap separately. A net-of-VAT budget does not establish the total cash needed on each supplier payment date.

The annual example depreciates £150,000 over ten years and £30,000 over five years, with no residual value: £21,000 a year. These are illustrative accounting lives, not tax allowances, construction warranties or promises about replacement timing. The £10,000 pre-opening costs are outside the stabilised trading-year P&L and must also be recognised appropriately in the launch accounts.

Interest is modelled as 6% of the opening £100,000 loan balance and principal payments as £10,000 over the illustrated year. This is an allowance for comparison, not a lender’s quote or a full amortisation schedule. Replace it with dated drawdowns, interest and repayment amounts. Do not deduct principal from profit or use EBITDA as a complete debt-service cash-flow measure.

For a slow-start illustration, suppose the first three months achieve only half the target completed hours in each band, using one quarter of the annual cost and debt allowances. Contribution falls to £13,577.25 against £21,250 of fixed costs and £4,000 of debt payments: a £11,672.75 cash deficit on those items. The £40,000 operating reserve falls to £28,327.25, leaving the £20,000 construction contingency untouched. This simplified quarter is not a winter forecast or a complete bank reconciliation; wages, rent deposits, VAT and supplier payment dates need a monthly plan with checks inside each month.

Budget for replacement as well as routine upkeep. The LTA construction guidance recommends £1,500 per court annually for surface, lamp and column replacement, with additional consideration for structures, glass and any canopy. The £3,000 earmarking above covers only that two-court illustration; obtain a full lifecycle schedule from the contractor. Retaining a reserve does not remove depreciation or guarantee enough cash for a major repair.

Make the site evidence part of the decision

Keep a short evidence file beside the forecast. The decisive items are the permitted operating hours and lighting conditions; noise and access constraints; lease rights and obligations; surveys and a complete construction specification; achieved prices and repeat demand by band; the staffing and emergency rota; and a dated cash-payment schedule. Mark documents still to obtain rather than describing them as secured.

For this England example, check the proposal with the local planning authority before committing to a site or build. The LTA guidance also highlights site-specific engineering, drainage and the impact of noise and lighting on neighbours. A landlord’s agreement or an equipment supplier’s quotation does not settle the planning position. Scotland, Wales and Northern Ireland have their own planning systems.

Set responsibilities for court inspections, glass and surface maintenance, safe access, emergency arrangements and appropriate insurance. If seeking LTA venue registration, use the LTA safeguarding standards to check policies, welfare arrangements, relevant criminal-record checks and coaching accreditation. Registration standards are not a substitute for the operator’s other duties. Adding junior coaching or events changes both the operating plan and the hours available for ordinary hire.

The next decision is whether evidence supports the proposed timetable and leaves enough money for finance, replacement and the launch period. If it does not, revise the site cost, pricing, funding or scale before committing. To develop your own forecast, explore the Bsness padel club business plan software and replace the assumptions with verified inputs. This worked example has been calculated independently for the article; it is not a tested output of that product, a valuation or a funding approval.