After launch, use your business plan to make the next operating decision: compare completed trading results with the original assumptions, explain the important differences and update what you now expect to happen. Keep the original budget, actual results and latest forecast separate. Changing the forecast should not erase what the business originally intended to achieve.
A useful monthly review ends with a decision, someone responsible for it and a revised forward view. The example below follows a small bicycle repair business through its first month: a higher selling price partly offsets fewer completed jobs, while unpaid invoices explain why sales and cash received differ.
Keep three versions of the numbers
Your original budget records the assumptions agreed before trading: expected jobs, prices, costs, investment and payment dates. Preserve a dated copy. Your actual results record what happened during a defined period, with provisional items identified. Your latest forecast estimates the months ahead using the evidence now available.
These views answer different questions. The budget shows the starting intention; actuals show the outcome; the forecast helps decide what resources and cash are now needed. Do not replace a missed budget with a lower forecast and then report that the original target was achieved.
Invest Northern Ireland’s guidance on keeping finance forecasts up to date describes retaining the original budget alongside variances and new forecasts. It also explains rolling forecasts: as a month’s actual figures are finalised, extend the forward view by another month to retain a 12-month projection. This is management guidance, not a compulsory reporting calendar for every UK business.
Keep operational assumptions alongside the money. A forecast of 40 repairs needs available workshop time, parts and customers. An empty appointment slot is capacity; it is not evidence of a future booking.
Close the month before judging performance
Choose a reporting cut-off and gather records that cover the same period. For a small business, the owner and bookkeeper can start with completed jobs, invoices and credits, supplier costs, unpaid customer invoices, upcoming bills and the reconciled bank balance.
- Check what “sales” means. Keep enquiries, accepted bookings, completed work, invoices and bank receipts distinct. Check work completed but not yet invoiced and payments received for work still to be delivered.
- Check the cost cut-off. Include costs incurred for the period even if the supplier invoice has not arrived. Mark an estimate as provisional and replace it when confirmed. A missing bill is not a saving.
- Use consistent classifications. Keep the same VAT basis, units and cost categories in budget and actuals. Separate stock or equipment purchases, operating costs, finance payments and owner withdrawals where they arise.
- List exceptions that could change the decision. Flag refunds, disputed invoices, missing costs, rework and one-off events. Do not wait for perfect information to address a payment that is about to become unaffordable.
Then review the few measures that matter to the next decision. For definitions, targets and milestone design, use the separate guide to monitoring a business plan with KPIs and milestones. Here the task is to turn those results into a revised operating plan.
A first-month review: fewer repairs at a higher price
Illustrative exercise, not a client case or UK market benchmark. Consider a UK sole trader repairing bicycles. The business is assumed not to be VAT registered; it charges no VAT and includes irrecoverable VAT in its costs. The owner performs the work, with no employees. Jobs are treated as one comparable type to keep the calculation simple.
The model includes specified variable cash costs for parts, consumables, local travel and payment charges, plus £500 of fixed cash operating costs for workshop use, insurance and basic administration. It excludes an allowance for the owner’s labour, depreciation, interest, tax and any other unlisted costs. It is a management exercise, not a complete profit forecast or tax calculation.
| First month | Original budget | Actual, in this exercise |
|---|---|---|
| Completed and invoiced jobs | 40 | 30 |
| Average realised price per job | £80 | £90 |
| Sales invoiced | £3,200 | £2,700 |
| Variable cost per job | £20 | £22 |
| Total specified variable costs | £800 | £660 |
| Contribution towards fixed costs and the remaining result | £2,400 | £2,040 |
| Specified fixed cash costs | £500 | £500 |
| Remaining after these costs, before exclusions | £1,900 | £1,540 |
The arithmetic is £3,200 − £800 − £500 = £1,900 in the budget, compared with £2,700 − £660 − £500 = £1,540 in the exercise’s actuals. The £360 shortfall can be explained in three steps:
- Fewer jobs: (30 − 40) × the budgeted £60 contribution per job = −£600.
- Higher average price: 30 × (£90 − £80) = +£300.
- Higher variable cost per job: 30 × (£22 − £20) = −£60 on the result.
So £1,900 − £600 + £300 − £60 = £1,540. Spending £140 less on variable costs in total is not evidence of better purchasing: there were fewer jobs, and cost per job increased. At the actual 30-job volume, the original £20 cost assumption would have allowed £600, against £660 incurred.
This is the principle of comparing costs at the actual activity level, described in ACCA’s guidance on flexible and flexed budgets. It depends on understanding which costs vary with volume and when fixed or stepped costs change.
The bridge explains the numerical difference; it does not establish the business cause. Check the job log and quotations: were there fewer enquiries, more cancellations, limited opening hours or longer repairs? Was the higher average price a genuine price change or a different mix of work? If jobs differ substantially, analyse comparable groups rather than treating every repair as equivalent.
Sales invoiced are not cash received
Assume £2,100 of the £2,700 invoiced was received by month end, with £600 still unpaid and due in the following month. There were no opening receivables, refunds or other sales adjustments in this exercise. The £600 difference is a payment-timing issue to track, not another reduction in invoiced sales.

With £1,000 opening cash and all £660 variable costs and £500 fixed costs paid, closing cash would be £1,000 + £2,100 − £660 − £500 = £1,940. This assumes no equipment purchases, borrowing, repayments, taxes, personal withdrawals or other cash flows. The £1,540 operating remainder and £940 cash increase differ by the £600 still to collect; neither is the owner’s take-home pay. Use the financial forecast guide to build the complete cash and profit views.
Turn the finding into a new forecast and an action
Suppose the original second-month budget also assumed 40 jobs at £80. After the review, the owner provisionally forecasts 32 jobs at £90 and £22 variable cost per job, with fixed costs still £500. These are new assumptions to test, not sales already secured. Check appointment length, available working time, parts and customer demand before adopting them.
The revised second-month sales forecast is 32 × £90 = £2,880; contribution is 32 × (£90 − £22) = £2,176. After the specified £500 fixed costs, £1,676 remains before the same exclusions. Retain the original £3,200 sales budget beside this forecast. Do not fill the ten missing first-month jobs into month two merely to restore the original annual target.

Update receipts separately. If all £2,880 of second-month sales are paid in that month and the earlier £600 arrives, receipts would be £3,480. If that £600 arrives later, receipts would be £600 lower. Rebuild the dated cash forecast with all payments and withdrawals before committing funds; these receipts alone do not establish a safe cash balance.
A useful action note would be: “Owner to review the unconverted quotations and cancellations, check the reasons with the available records, and reassess the 32-job forecast at the next weekly booking review.” Add the actual deadline, evidence and outcome in your own plan. Do not claim that a demand investigation has happened until it has.
Keep observation, explanation and decision separate: “30 jobs completed” is an observed result in the exercise; “demand was too weak” is a possible explanation; “reduce next month’s forecast” is a decision. A shortfall alone does not prove which explanation is correct. Record what would cause you to revise the decision again.
Review often enough to change the outcome
For this exercise, weekly checks of bookings, missing parts and receipts help the owner act before month end. A monthly review follows the reconciled results. A wider strategic review is needed when the customer proposition, capacity or funding changes materially. These are proposed choices for the case, not a universal UK timetable.
The British Business Bank’s review guidance links reassessment to resource allocation and changing business conditions. Invest Northern Ireland’s guidance also describes regular reviews and earlier reassessment when major events affect the business. Do not wait for a scheduled meeting if a forthcoming payment cannot be covered.
Finish each review with a dated comparison, an explanation of the material differences and uncertainties, an updated forecast, and an action with an owner and deadline. Update only the affected parts of the narrative: customer assumptions, operating capacity, pricing, marketing or funding. A routine monthly close does not require rewriting the whole business plan.
If a lender needs an update, follow its actual information request and explain changes transparently. A tidy review pack does not itself establish regulatory compliance or guarantee finance. To connect these workings with the wider plan, explore Bsness business plan software, keeping original assumptions and revised expectations traceable.